Directional drilling unit UNB-30

Work performance from a pit (2.3 m x 1.3 m) Boring from the surface
Design and manufacture of the directed boring unit UNB-30 was stipulated by the following tasks:
- It must have small sizes to the maximum extent;
- Underground channels are to be worked out for subsequent installation of pipes having diameter from 63 mm to 160 mm at a distance by 100 running meters.
- Boring parameters are to be determined with the aid of the location system and drill travel direction is to operatively be adjusted in plan and profile.
- Possibility of drilling work performance both from the soil surface and from a small pit during mechanism installation to a duct, what makes it possible to optimally choose the method of trenchless installation of pipelines under conditions of city construction.
- Pipelines are to be replaced without excavations.
SPECIFICATIONS OF UNB-30 EQUIPMENT SET:
|
|
PARAMETERS |
SPECIFICATIONS |
|
1 |
Overall dimensions of power unit in a duct, mm |
Length: 2330 |
|
2 |
Hydraulic plant: |
Power 17.7 kW |
|
3 |
Hydraulic cylinder: |
200 kg/cm3 |
|
4 |
Pump: |
30 l/min |
|
5 |
Hydraulic tank: |
110 l 270 kg |
|
6 |
Control unit |
RD – 385 L |
|
7 |
Working interval of temperatures: |
-20ºŃ ... +40ºŃ |
|
8 |
Traction force: |
22.5 t 30.0 t |
|
9 |
Boring parameters: |
by 60 m by 100 m 160 mm |
|
10 |
Total weight of the basic set of equipment |
0.9 t |